Summer Update

  • Published 2019-07-15

Otis Fiber Phase 4 installations have begun and should be complete by mid to late August. Strand and Fiber are being run in Phases 7, 8, 9. Installation of MST’s, splicing, and testing is ongoing in Phase 6 and the fiber hut at the center of town is due to go online the week of July 15. We are hopeful the project will be complete by the end of the year.